List of OSC references:

No. Description Object Year
1Project and implementation of steam turbine 120 MW control in power station Ambarli (Turkey)Power plant Ambarli (Turkey)2011 - 2012
2Control loop tuning and units ancillary services certification in power plant Prunéřov 1ČEZ, a.s. - Power plant Prunéřov 12007 - 2012
3Certification measurement of ancillary services “primary, secondary a tertiary power control” in power plant OpatoviceElektrárny Opatovice, a.s. - Power plant Opatovice2004 - 2012
4Implementation of boiler control algorithms in heating station Košice (Slovakia)Teplárna Košice, a.s. - Heating station Košice (Slovakia)2011 - 2012
5Feasibility study of operational possibilities of heating station Planá nad Lužnicí to provide ancillary services and certification of ancillary service “quick starting reserve available within 15 minutes“AES Bohemia spol. s r.o. - Heating station Planá nad Lužnicí2010 - 2011
6Delivery of GPSNTP time servers with active antenna, surge protectors and power supplyAISE, spol. s r.o.2011
7Delivery of DT20-6 ethernet LED digital clockALES, spol. s r.o.2011
8Delivery of GNTP time servers with active antenna, surge protectors and power supplyALES, spol. s r.o.2011
9Delivery of GPSNTP time servers with active antenna, surge protectors and power supplyALES, spol. s r.o.2011
10Feasibility study of unit remote control in island operationČEPS, a. s.2011
11Island mode of distribution system - influence study of distributed energy resourcesČEZ Distribuce, a. s.2011
12Hydro system Resita identification measurement of pumping station and hydro power plants before rehabilitation (Romania)ČEZ Romania - Hydro system Resita (Romania)2011
13Feasibility study of changes in ancillary services from January 2013 for ČEZ Central dispatch center and Power plants TerminalsČEZ, a.s.2011
14Delivery of GPSD (GPS central time system) with slave clock driverČEZ, a.s. - Hydro power plant Štěchovice2011
15Tuning of boiler control loops in power plant DětmaroviceČEZ, a.s. - Power plant Dětmarovice2003 - 2011
16Delivery of GPSNTP time servers with active antennaČEZ, a.s. - Power plant Dětmarovice2011
17Control of cooling water flow in power plant Chvaletice - control algorithm design, implementation and operational setupČEZ, a.s. - Power plant Chvaletice2009 - 2011
18Power plant Terminal project of combined cycle PočeradyČEZ, a.s. - Power plant Počerady2011
19Delivery of GPSNTP time servers with active antenna and power supplyČEZ, a.s. - Power plant Prunéřov2011
20Certification measurement of ancillary service “island operation capability” in power plant Prunéřov 2ČEZ, a.s. - Power plant Prunéřov2003 - 2011
21Certification measurement of ancillary services “primary, secondary, tertiary power control and island operation” in power plant Prunéřov 2ČEZ, a.s. - Power plant Prunéřov 22003 - 2011
22Control circuits tuning and units preparation for ancillary services certification in power plant Prunéřov 2ČEZ, a.s. - Power plant Prunéřov 22001 - 2011
23Guarantee measurement of boiler dynamic properties after equipment modernizationČEZ, a.s. - Power plant Prunéřov 22011
24Certification measurement of ancillary services “quick starting reserve” in pumped storage power plant ŠtěchoviceČEZ, a.s. - Pumped storage power plant Štěchovice2007 - 2011
25Certification measurement of ancillary services “primary, secondary and tertiary power control” in heating station OlomoucDalkia Česká republika, a.s. - Heating station Olomouc2005 - 2011
26Certification measurement of ancillary services “primary, secondary, tertiary power control and quick starting reserve available within 15 minutes” in heating station PřerovDalkia Česká republika, a.s. - Heating station Přerov2005 - 2011
27Preparation, realization and certification of primary control in heating station PřerovDalkia Česká republika, a.s. - Heating station Přerov2007 - 2011
28Delivery of Power plant Terminal for power plant Malženice (Slovakia), implementation of support to provide ancillary services, power supply control, measuring and evaluation of gas consumptionE.ON Elektrárne, s.r.o. - Power plant Malženice (Slovakia)2011
29Delivery of information center for power plant Malženice (Slovakia) - data and terminal function accessible via intranet and internet, support for production planning and evaluationE.ON Elektrárne, s.r.o.. - Power plant Malženice (Slovakia)2011
30Identification measurement of Kaplan turbine before reconstruction in hydro power plant Betsele (Sweden)E.ON Vattenkraft Sverige AB - Hydro power plant Betsele (Sweden)2011
31Guarantee measurement of Kaplan turbine in small hydro power plant Vír IIE.ON, a.s. - Small hydro power plant Vír II2011
32Performance tests of Francis turbines at hydro power plant Santa Barbara (Nicaragua)Enel Nicaragua - Hydro power plant Santa Barbara (Nicaragua)2011
33Feasibility study of dispatch centers for renewable energy resourcesEuroenergy, spol. s r.o.2011
34Power plant Terminal project of heating station ProstějovGama Investment, a.s. - Heating station Prostějov2011
35Upgrade of Power plant Terminal in combined cycle Bratislava (Slovakia) afrer new power unit constructionPPC Energy, a.s. - Combined cycle Bratislava (Slovakia)2010 - 2011
36Upgrade of Power plant Terminal and information center in Combined cycle Bratislava (Slovakia) to fulfil ancillary service requirements (tertiary power control available within 10 minutes)PPC Power, a.s., PPC Energy a.s. - Combined cycle Bratislava (Slovakia)2011
37Shutdown tests on water supply pipe at waterworks KáranýPražské vodárny, s.p. - Water company Káraný2011
38Delivery of GPSNTP time servers with active antenna, surge protectors and power supplyProjectSoft HK, a.s.2011
39Status identification of boiler technology in Power plant Deva (Romania)S.C. Electrocentrale Deva S.A. - Power plant Deva (Romania)2011
40Delivery of GPSNTP time servers with active antenna, surge protectors and power supplySiprin, spol. s r.o.2011
41Optimization of on-cam correlation at Kaplan turbine in hydro power plant Orava (Slovakia)Slovenské elektrárne, a.s. - Hydro power plant Orava (Slovakia)2011
42Ancillary services certification measurement “primary, secondary and tertiary power control” in Combined cycle VřesováSokolovská uhelná, právní nástupce, a.s. - Combined cycle Vřesová2001 - 2011
43Measurement of pressure, vibration and noise at polyjet of hydro power plant Trollheim (Norway)Statkraft Energi AS - Hydro power plant Trollheim (Norway)2010 - 2011
44Duplication of Power plant Terminal in heating station TrmiceTeplárna Trmice, a.s. - Heating station Trmice2011
45Duplication of Power plant Terminal in heating station Červený mlýnTeplárny Brno, a.s. - Heating station Červený mlýn2011
46Hydro power plants Eldforsen (Sweden) - tests relevant to Kaplan turbine during putting into operationHydro power plant Eldforsen (Sweden)2010
47Pressure and vibration measurement in the water spray sealing of hydro power plant Josefův DůlHydro power plant Josefův Důl2010
48Hydro power plant Poechos (Peru) - tests relevant to Kaplan turbines during putting into operationHydro power plant Poechos (Peru)2010
49Delivery of power plant terminal to provide ancillary service “quick starting reserve available within 15 minutes” for heating station Planá nad LužnicíAES Bohemia spol. s r.o. - Heating station Planá nad Lužnicí2010
50Delivery of 3 pieces of GPSNTP time servers with active antenna, overvoltage protections and power supplyAISE, s.r.o.2009 - 2010
51Delivery of 1 piece of GPSNTP time server with active antennaAutocont CZ, a.s.2010
52Island mode of distribution systems - technical specification of active separation of islands for areas Neznášov south, Neznášov north, Opočínek, Přerov and LískovecČEZ Distribuce, a. s.2009 - 2010
53Optimization of on-cam correlation on Kaplan turbine, turboset vibration and noise measurement in small hydro power plant HracholuskyČEZ Obnovitelné zdroje, s.r.o. - Small hydro power plant Hracholusky2010
54Guarantee measurement of Kaplan turbine in small hydro power plant KníničkyČEZ Obnovitelné zdroje, s.r.o. - Small hydro power plant Kníničky2010
55Optimization of on-cam correlation at Kaplan turbine in small hydro power plant PředměřiceČEZ Obnovitelné zdroje, s.r.o. - Small hydro power plant Předměřice2010
56Guarantee measurement of Kaplan turbines in small hydro power plant SpytihněvČEZ Obnovitelné zdroje, s.r.o. - Small hydro power plant Spytihněv2009 - 2010
57Extension of presentation layer technology in an intranet environment of ČEZ for data display of commercial activitiesČEZ, a.s.2010
58Upgrade of control system KOTEL in Dispatch Center ČEZ and upgrade of power plant terminals to provide for ancillary service according to conditions for year 2011 (quick starting reserve available within 15 minutes, asymmetric secondary power control, diagram changes during ancillary services providing)ČEZ, a.s.2010
59Determination of turbo-set operation diagram in hydro power plant SlapyČEZ, a.s. - Hydro power plant Slapy2003 - 2010
60Diagnostics of reasons of high carbon content in fly ash in power plant DětmaroviceČEZ, a.s. - Power plant Dětmarovice2010
61Energetic parameters measurement and judgment of ceramic coating ARC 32 influence in cooling water pump in power plant ChvaleticeČEZ, a.s. - Power plant Chvaletice2009 - 2010
62Assessment of abilities of unit in power plant Prunéřov 1 for certification of ancillary service “secondary power control” and “tertiary power control”ČEZ, a.s. - Power plant Prunéřov 12010
63Proposal, modification and tuning of control circuits for transition of units Prunéřov 1 from turbine-follow mode into boiler-follow mode operationČEZ, a.s. - Power plant Prunéřov 12002 - 2010
64Migration of control system (WDPF II to Ovation) of units B21 and B22 in power plant Prunéřov 2 – system migration, put into operation, start-upČEZ, a.s. - Power plant Prunéřov 22010
65Control of cooling water flow in power plant Tušimice - design of control algorithmČEZ, a.s. - Power plant Tušimice2010
66Governor tests of reverse Francis turbines before and after control system replacement in pump storage plant Dlouhé StráněČEZ, a.s. - Pumped storage power plant Dlouhé Stráně2007 - 2010
67Feasibility study of operating options of heating station Karviná to provide ancillary services and Study on possible configurations of fictive unit according to Grid CodeDalkia Česká republika, a.s. - Heating station Karviná2010
68Certification of ancillary services “primary power control”, “tertiary power control” and “quick starting reserve available within 15 minutes” at heating station KarvináDalkia Česká republika, a.s. - Heating station Karviná2010
69Terminal duplication of heating station Karviná and preparation for direct connection to ČEPS Dispatch Center.Dalkia Česká republika, a.s. - Heating station Karviná2010
70Certification of ancillary service “quick starting reserve available within 15 minutes“ at fictive unit of heating station OlomoucDalkia Česká republika, a.s. - Heating station Olomouc2010
71Upgrade of heating stations Olomouc and Přerov terminals to provide ancillary service “quick starting reserve available within 15 minutes”Dalkia Česká republika, a.s. - Heating station Olomouc, Heating station Přerov2010
72Certification measurement of ancillary services “secondary and tertiary power control” of fictive unit in heating station TrmiceDalkia Česká republika, a.s. - Heating station Ústí nad Labem2005 - 2010
73Certification of ancillary service “quick starting reserve available within 15 minutes“ in plant Kolin-ZalabiDalkia Kolín, a.s. - Power plant Kolín2010
74Upgrade of plant Kolin terminal to provide ancillary service “quick starting reserve available within 15 minutes”Dalkia Kolín, a.s. - Power plant Kolín2010
75Guarantee measurement of Francis turbines in small hydro power plant SoběnovE.ON Trend s.r.o. - Small hydro power plant Soběnov2009 - 2010
76Identification measurement of Francis turbines before reconstruction in hydro power plant Lapino (Poland)ENERGA Elektrownie Straszyn Sp. z o.o. - Small hydro power plant Lapino (Poland)2010
77Guarantee measurement of Francis turbines in small hydro power plant MeziboříEnergo-Pro Czech, s.r.o. - Hydro power plant Meziboří2010
78Guarantee measurement of Pelton turbines (thermodynamics method) and governors in hydro power plant Zrnovci (Macedonia)MacHydro Project, a.d. - Hydro power plant Zrnovci (Macedonia)2010
79Guarantee measurement of Kaplan and Francis turbines in small hydro power plant NymburkMVE Hydro, s.r.o. - Small hydro power plant Nymburk2010
80Guarantee measurement of Francis turbines in small hydro power plant Ampelgading (Indonesia)PLN Indonesia - Hydro power plant Amplegading (Indonesia)2010
81Connection of newly built unit for biomass combustion (Plzeňská teplárenská) to terminal of heating station PlzeňPlzeňská teplárenská, a.s. - Heating station Plzeň2010
82Guarantee measurement of Kaplan turbine in small hydro power plant TrojaPovodí Vltavy, s.p. - Small hydro power plant Troja2010
83Guarantee measurement of Kaplan turbine in small hydro power plant LabskáPrvní ekologická, a.s. - Small hydro power plant Labská2010
84Feasibility study of ancillary services providing according to Grid Code for Příbramská teplárenská and certification measurement of ancillary service "primary control" in heating station PříbramPříbramská teplárenská, a.s. - Heating station Příbram2009 - 2010
85Guarantee measurement of Kaplan turbine in small hydro power plant Rendelstein (Italy)Rendelstein GmbH - Small hydro power plant Rendelstein (Italy)2010
86Exchange of combustion turbine GE control system in power plant Fellside (Great Britain) – reimplementation of algorithmsSellafield CHP, Ltd. - Power plant Fellside2009 - 2010
87Optimization of on-cam correlation at Kaplan turbine in hydro power plant Kostolná (Slovakia)Slovenské elektrárne, a.s. - Hydro power plant Kostolná (Slovakia)2010
88Delivery of power plant terminal and certification of ancillary service "tertiary power control" in fictive unit of heating station Teplárna OtrokoviceTeplárna Otrokovice, a.s. - Heating station Otrokovice2009 - 2010
89Certification of ancillary service “quick starting reserve available within 15 minutes“ at fictive unit of heating station OtrokoviceTeplárna Otrokovice, a.s. - Heating station Otrokovice2010
90Upgrade of heating station Trmice terminal to provide ancillary service “quick starting reserve available within 15 minutes”Teplárna Trmice, a.s. - Heating station Trmice2010
91Certification of ancillary service “quick starting reserve available within 15 minutes“ at fictive unit of heating station TrmiceTeplárna Trmice, a.s. - Heating station Trmice2010
92Project of power plant terminal for newly built peak power plant Brno - NorthTeplárny Brno, a.s.2010
93Certification of ancillary service “quick starting reserve available within 15 minutes“ and “dispatcher reserve available within 30 minutes” at combined cycle Červený mlýnTeplárny Brno, a.s. - Combined cycle heating station Červený mlýn2006 - 2010
94Certification measurement of ancillary services “secondary and tertiary power control” in combined cycle heating station Červený mlýnTeplárny Brno, a.s. - Combined cycle heating station Červený mlýn2002 - 2010
95Guarantee measurement of low-head Kaplan turbines before and after reconstruction in hydro power plant TiszalökTiszavíz Vízerömü Kft - Hydro power plant Tiszalök (Hungary)2004 - 2010
96Delivery of 1 piece of GPSNTP time server with active antennaUniversity of California, Santa Barbara (USA)2010
97Guarantee measurement of Kaplan turbines in small hydro power plant Penz (Austria)VAEE - Small hydro power plant Penz (Austria)2010
98Optimization of on-cam correlation on Kaplan turbine in hydro power plant Lakatnik (Bulgaria)VEZ SVOGHE - Small hydro power plant Lakatnik (Bulgaria)2010
99Upgrade of power plant Burštýn (the Ukraine) terminal with redundancy of all units and installation GPSD for time synchronizationZakhidenergo - Power station Burštýn (the Ukraine)2010
100Delivery of 1 piece of GPSNTP time server with active antennaAstronomický ústav AV ČR, v.v.i.2009
101Connection of power plant terminals to nett energy trade measurement in ČEZ, a.s.ČEZ, a.s.2009
102Modification of control system KOTEL in Dispatch centre of ČEZ for control of nett energy delivery error of ČEZ, a.s.ČEZ, a.s.2009
103Miniterminal instalation for heating plant Dvur Kralove nad Labem monitoring by CEZ Dispatch CenterČEZ, a.s. - Heating station Dvůr Králové nad Labem2009
104Energetic parameters measurement and judgment of ceramic coating ARC 32 influence in cooling water pump in nuclear power plant DukovanyČEZ, a.s. - Nuclear power plant Dukovany2008 - 2009
105Cooling pump operation control in power plant DětmaroviceČEZ, a.s. - Power plant Dětmarovice2006 - 2009
106Certification measurement of ancillary services “primary, secondary and tertiary power control” and “operating reserve” in power plant DětmaroviceČEZ, a.s. - Power plant Dětmarovice2006 - 2009
107Study on possibilities of ancillary services control changes and their testing in power plant PočeradyČEZ, a.s. - Power plant Počerady2009
108Turboset vibration and noise measurement before reconstruction in small hydro power plant KníničkyČEZ, a.s. - Small hydro power plant Kníničky2009
109Efficiency and flow measurement of Kaplan turbine in small hydro power plant Lipno IIČEZ, a.s. - Small hydro power plant Lipno II2009
110Power plant terminals modification in heating stations Olomouc, Přerov and Ústí nad Labem for cooperation with Damas Energy systémDalkia Česká republika, a.s. - Heating station Olomouc, Heating station Přerov, Heating station Ústí nad Labem2009
111Preparation of TG5 in Dalkia Kolín to provide ancillary service "primary power control"Dalkia Kolín, a.s. - Power plant Kolín2009
112Preparation of fictive unit Dalkia Ústí nad Labem to provide ancillary service "secondary power control" including certification of this ancillary service in certain operation modes of fictive unitDalkia Ústí nad Labem, a.s. - Heating station Trmice2009
113Duplication of communication processor of power plant Opatovice because of reliability increaseElektrárny Opatovice, a.s. - Power plant Opatovice2009
114Guarantee measurement in hydro power plants Hradištko and KostomlátkyEnergo-Pro Czech, s.r.o. - Hydro power plants Hradištko and Kostomlátky2007 - 2009
115Delivery of 1 piece of GPSNTP time servers with active antenna and power supplyLandis&Gyr, s.r.o.2009
116Guarantee measurement of Pelton turbines using thermodynamics method, measurement of generator loss in hydro power plant DošnicaMacHydro Project, a.d. - Hydro power plant Došnica (Macedonia)2009
117Guarantee measurement of Pelton turbines using thermodynamics method, measurement of generator loss in hydro power plant SapunčicaMacHydro Project, a.d. - Hydro power plant Sapuncica (Macedonia)2009
118Turboset noise measurement in small hydro power plant NymburkMVE - HYDRO s.r.o. - Small hydro power plant Nymburk2009
119Delivery of 2 pieces of GPSNTP time servers with active antenna and extension cordProjectSoft HK, a.s.2009
120Turboset noise measurement in small hydro power plant Kostelec nad LabemRida Consulting, a.s. - Small hydro power plant Kostelec nad Labem2009
121Control system replacement of combustion turbines GEC Alsthom in power plant Arar (Saudi Arabia) - setting into operationSEC - Al Jouf Power plant (Saudi Arabia)2009
122Control system replacement of combustion turbine Fiat in power plant Al Jouf (Saudi Arabia) - algorithm implementation and setting into operationSEC - Al Jouf Power plant (Saudi Arabia)2008 - 2009
123Control system replacement of combustion turbine GE in power plant Makkah (Saudi Arabia) - algorithm implementation and setting into operationSEC - Makkah Power plant (Saudi Arabia)2007 - 2009
124Judgement on turboset load decrease of pumped storage power plant Čierny VáhSlovenské elektrárne, a.s. - Pumped storage power plant Číerny Váh (Slovakia)2009
125Guarantee measurement of Kaplan turbine in small hydro power plant HracholuskyStrojírny Brno, a.s. - Small hydro power plant Hracholusky2009
126Guarantee measurement of Kaplan turbines in small hydro power plant Lakatnik and Svrajen (Bulgaria)VEZ SVOGHE - Small hydro power plant Lakatnik and Svrajen (Bulgaria)2009
127Delivery of 4 pieces of GPSNTP time servers with active antenna and power supplyVodafone Czech Republic, a.s.2009
128Delivery of 1 piece of GPSNTP time server with active antennaZAT, a.s.2009
129Analyse of possibilities and conditions of ancillary services providing in heating station ZlínAtel Zlín, s.r.o. - Heating station Zlín2008
130Island mode of distribution system - specification of islands selected for active island setting up during troubles in electric power systemČEZ Distribuce, a. s.2008
131Simulator for Dispatch centre of ČEZ. It provides staff training and proving of control system KOTEL algorithms. The simulator includes the complete models of the control system, connected power plant terminals and production technologyČEZ, a.s.2008
132Modification of control system KOTEL (Dispatch centre of ČEZ) for balancing of produced energy in trading intervalČEZ, a.s.2008
133Certification measurement of ancillary services “island operation capability” , "black start capability" and “quick starting reserve” in hydro power plant OrlíkČEZ, a.s. - Hydro power plant Orlík2006 - 2008
134Continual measurement of amount of cooling water from Labe river for power plant MelnikČEZ, a.s. - Power plants Mělník2008
135Connection of terminals of power plants Prunéřov 1 and Prunéřov 2 with voltage node control system in Hradec u Kadaně. It provides remote voltage control from power plants and monitoring from Dispatch centre ČEZČEZ, a.s. - Power plants Prunéřov2008
136Monitoring of power plant operation from Dispatch centre of ČEZ for power plants Skawina and Chorzow (both Poland) - instalation of miniterminalsČEZ, a.s. - Power plants Skawina a Chorzow (Poland)2008
137Compliance test and guarantee measurement of control circuits in pumped-storage power plant DalešiceČEZ, a.s. - Pumped storage power plant Dalešice2003 - 2008
138Turbo-set guarantee measurement in pumped-storage power plant DalešiceČEZ, a.s. - Pumped storage power plant Dalešice2003 - 2008
139Proposal of island operation of heating station Přerov, technical cooperation during modification and test of island operation (self-consumption of heating station)Dalkia Česká republika, a.s. - Heating station Přerov2006 - 2008
140Study on possibilities of operational extension to provide ancillary services for Dalkia ČR, department Ústí nad LabemDalkia Česká republika, a.s. - Heating station Trmice2007 - 2008
141Feasibility study of black start in heating station PřerovDalkia Česká republika, a.s., Divize Přerov - Heating station Přerov2008
142Delivery and installation of 1 piece of GPSNTP time server with active antenna and delivery of NTP client (multilicence for 60 users). Time synchronization of client devices in technology networkElektrárny Opatovice, a.s. - Power plant Opatovice2008
143Guarantee measurement in hydro power plant Kroměříž – StržEnergo-Pro Czech, s.r.o. - Hydro power plant Kroměříž - Strž2005 - 2008
144Guarantee measurement of Pelton turbines and generator losses measurement in hydro power plant PatikariEnergy Infratech PVT. LTD. - Hydro power plant Patikari (India)2008
145Supervision of Kaplan turbine production in ČKD Blansko for power plant Eldforsen (Sweden)Fortum Generation AB - Hydro power plant Eldforsen (Sweden)2008
146Guarantee measurement of Francis turbines and governors in hydro power plant ConcepciónIsmus CE - Hydro power plant Concepción (Panama)2008
147Guarantee measurement of Kaplan turbines and governors and generator losses measurement in hydro power plant Matka IIMacHydro Project, a.d. - Hydro power plant Matka (Macedonia)2008
148Guarantee measurement of Pelton turbines and governors and generator losses measurement in hydro power plant PesocaniMacHydro Project, a.d. - Hydro power plant Pesocani (Macedonia)2008
149Guarantee measurement of Pelton turbines and governors and generator losses measurement in hydro power plant SapuncicaMacHydro Project, a.d. - Hydro power plant Sapuncica (Macedonia)2008
150Delivery of 5 pieces of GPSNTP time servers with active antenna and power supplyNárodní bezpečnostní úřad ČR2008
151Software and hardware upgrade for terminal of power plant Burštýn (the Ukraine) - communication with Dispatch centre RDC Lvov via protocol IEC - 870 - 5 - 104, automatic stand-by of control units, frequency measurement and time synchronization from GPSOAO Zachidenergo - Power plant Burštýn (the Ukraine)2002 - 2008
152Guarantee measurement of axial Kaplan turbine in small hydro power plant RozkošPovodí Labe, s.p. - Small hydro power plnat Rozkoš2008
153Certification measurement of ancillary service "Island operation" in combined heat and power plant "Paroplyn kombinátu Vřesová"Sokolovská uhelná, právní nástupce, a.s. - Combined heat and power plant Vřesová2007 - 2008
154Optimization of on-cam correlation on Kaplan Turbines in hydro power plant LíšnýTEODICEA, spol. s r.o. - Hydro power plant Líšný2007 - 2008
155Study on possibilities of black start in combined cycle heating station Červený mlýnTeplárny Brno, a.s. - Combined cycle heating station Červený mlýn2007 - 2008
156Island mode of distribution systems - solution philosophy and assessment of technical and operational conditions of plantsČEZ Distribuce, a. s.2007
157Voltage control system modification for remote setpoint adjusting in voltage junction in power plants Temelín, Dukovany, Počerady, Chvaletice and Dlouhé StráněČEZ, a.s.2002 - 2007
158Terminals modification of power plant ČEZ for Integrated dispatcher system of Transmission System OperatorČEZ, a.s.2007
159Reconstruction of plant data damaged by server failure or by communication failure between power plants and dispatcher center ČEZ in Wonderware HistorianČEZ, a.s.2007
160Updating hydro power plants data lists according to the actual stateČEZ, a.s.2003 - 2007
161Measurement of emergency valve stroke in hydro power plant OrlíkČEZ, a.s. - Hydro power plant Orlík2007
162Delivery of GPS time centers and DA20-8 displays for the renovation of the control system in nuclear power plant DukovanyČEZ, a.s. - Nuclear power plant Dukovany2000 - 2007
163Certification measurement of ancillary services “island operation capability”, “black start capability” and “quick starting reserve” in pump storage plant DalešiceČEZ, a.s. - Pumped storage power plant Dalešice2005 - 2007
164Terminals modification of power plant Dalkia Czech Republik for Integrated dispatcher system in Transmission System OperatorDalkia Česká republika, a.s.2007
165Certification of ancillary service DZ60 with extended control margin in Dalkia Czech Republic, division Ústí nad LabemDalkia Česká republika, a.s. - Heating station Trmice2007
166Power plant terminal delivery, technical cooperation during realization and certification of ancillary service tertiary control in power plant KolínElektrárna Kolín a.s. - Power plant Kolín2007
167Study on suitability of ancillary services providing in power plant Kolín, Study on operating possibilities and Study of possible operating configurations and variations in power plant Kolín for ČEPS, a.s.Elektrárna Kolín a.s. - Power plant Kolín2007
168Identification measurement of Francis turbine before reconstruction in hydro power plant MeziboříEnergo-Pro Czech, s.r.o. - Hydro power plant Meziboří2007
169Identification measurement of Francis turbine in hydro power plant SečEnergo-Pro Czech, s.r.o. - Hydro power plant Seč2007
170Communication processor extension in power plant Opatovice for monitoring of substation 110 kV from Dispatcher centre of ČEZ Distribuce, a.s.International Power Opatovice, a.s. - Power plant Opatovice2007
171Communication Processor delivery for power plant OpatoviceInternational Power Opatovice, a.s. - Power plant Opatovice2000 - 2007
172Delivery of backed-up dispatcher graphic system (DIGRAST) and backed-up energy measurement system for Jihočeská energetika companyJČE, a.s.2000 - 2007
173Guarantee measurement of Francis turbines and governors and generator losses measurement in hydro power plant PenaMacHydro Project, a.d. - Hydro power plant Pena (Macedonia)2007
174Delivery of Power plant terminal for Paroplynový cyklus (PPC), Bratislava, implementation of power supply control, gas consumption measuring and evaluationParoplynový cyklus, a.s. - Combined cycle Bratislava (Slovakia)2006 - 2007
175Delivery of information center for Paroplynový cyklus Bratislava - making datas and terminal function accessible via intranet and internetParoplynový cyklus, a.s. - Combined cycle Bratislava (Slovakia)2007
176Optimization of on-cam correlation on Kaplan turbines in hydro power plant NechranicePovodí Ohře, s.p. - Hydro power plant Nechranice2002 - 2007
177Kaplan turbine guarantee measurement in hydro power plant OravaSlovenské elektrárne, a.s. - Hydro power plant Orava (Slovakia)2006 - 2007
178Study on operating feasibilities for ancillary services providing for heating plant OtrokoviceTeplárna Otrokovice a.s. - Heating station Otrokovice2007
179Study of own-consumption determination for evaluation of supplied control powerČEPS, a.s.2006
180Delivery of Presentation Layer for technology data presentation in intranet of company ČEZ, Plc.ČEZ, a.s.2004 - 2006
181Control circuit tests and on-cam optimization of Kaplan turbine in hydro power plant Lipno IIČEZ, a.s. - Hydro power plant Lipno II2006
182Creation and testing of procedure for supervision and execution of control system algorithm modification in nuclear power plant TemelínČEZ, a.s. - Nuclear power plant Temelín2002 - 2006
183Connection between Power plant Terminal and voltage control system for tertiary voltage control implementation in power plant Mělník 3ČEZ, a.s. - Power plants Mělník2006
184Power unit examination before certification measurement of “primary, secondary and tertiary power control” and “island operation capability” in power plant Tisová 2ČEZ, a.s. - Power plants Tisová2006
185Turbine guarantee measurement before and after reconstruction in pumped-storage power plant DalešiceČEZ, a.s. - Pumped storage power plant Dalešice2000 - 2006
186Francis turbine guarantee measurement in small hydro power plant Les KrálovstvíČEZ, obnovitelné zdroje, s.r.o. - Hydro power plant Les Království2006
187Communication Processor delivery for Energetika Vítkovice companyEnergetika Vítkovice, a.s. - Energetika Vítkovice2006
188Proposal of airflow control aimed at limitation of NOx emission in power plant Mělník 1Energotrans, a.s. - Power plant Opatovice2005 - 2006
189Study on black start capability for power plant OpatoviceInternational Power Opatovice, a.s. - Power plant Opatovice2006
190Measurement of turbo-set efficiency and penstock losses in small hydro power plant SapunčicaMacHydro Project AD - Hydro power plant Sapunčica (Macedonia)2006
191Guarantee measurement of Francis turbines and control circuits in hydro power plant KalimanciMacHydro Project, a.d. - Hydro power plant Kalimanci (Macedonia)2006
192Francis turbine efficiency measurement and collection of data for reconstruction of hydro power plant MatkaMacHydro Project, a.d. - Hydro power plant Matka (Macedonia)2006
193Francis turbine efficiency measurement before reconstruction in hydro power plant PenaMacHydro Project, a.d. - Hydro power plant Pena (Macedonia)2006
194Pelton turbine efficiency measurement before reconstruction in hydro power plant PesocaniMacHydro Project, a.d. - Hydro power plant Pesocani (Macedonia)2006
195Pressure conditions tests in penstock of water plant Křižanovice – PráčovPovodí Labe, s.p. - Water plant Křižanovice - Práčov2006
196Kaplan turbine guarantee measurement in hydro power plant VraňanyPovodí Vltavy, s.p. - Hydro power plant Vraňany2006
197Certification measurement of ancillary services “secondary and tertiary power control” in department Teplárna in combined heat and power plant VřesováSokolovská uhelná, právní nástupce, a.s. - Combined cycle Vřesová2001 - 2006
198Power plant terminal upgrade – support for automatic stand-by functions for ancillary service controlSokolovská uhelná, právní nástupce, a.s. - Combined heat and power plant Vřesová2006
199Turbo-set guarantee measurement before and after overhaul in hydro power plant KisköreTiszavíz Vízerömü Kft - Hydro power plant Kisköre (Hungary)2005 - 2006
200Pressure conditions measurement in the supply pipeline Vír – BrnoVírský oblastní vodovod2006
201Optimization of on-cam correlation on Kaplan Turbines in hydro power plant ŽilinaVodohospodárska výstavba, š.p. - Water plant Žilina2006
202Francis turbine guarantee measurement before and after reconstruction in hydro power plant VydraZČE, a.s. - Hydro power plant Vydra2005 - 2006
203Efficiency measurement in small hydro power plant KadaňHydro power plant Kadaň2005
204Measurement of passive resistances and drive forces before reconstruction in hydro power plant Považská BystricaHydro power plant Povážská Bystrica (Slovakia)2005
205Kaplan turbine guarantee measurement in small hydro power plant PřeloučHydro power plant Přelouč2005
206Pump guarantee measurement in turbine operation mode in water purification plant in Nová BystricaWater purification plant Nová Bystrica (Slovakia)2005
207Certification methodology proposal for ancillary service “island operation capability” for hydro power plants and its incorporation into the Grid CodeČEPS, a.s.2005
208Delivery of KOTEL (Concentrator of Power plant Terminals) – information and control system of the Central dispatch centre of ČEZ, Plc. The KOTEL system supports operation scheduling, ancillary services provision, group power balancer and distributor, dynamic optimization and control of coal and pumped-storage power plantsČEZ, a.s.2000 - 2005
209Power plant terminals tests during preparation for control system duplication in Dispatch centre of the Transmission System OperatorČEZ, a.s.2005
210Voltage control system modification according to requirements of the Grid Code in power plants Počerady, Chvaletice and Dlouhé StráněČEZ, a.s.2005
211Key part Power plant Terminal duplication with automatic stand-by functions for ancillary services controlČEZ, a.s.2005
212Turbo-set efficiency measurement in hydro power plant LipnoČEZ, a.s. - Hydro power plant Orlík2005
213Cause detection of excessive turbo-set vibrations in hydro power plant SlapyČEZ, a.s. - Hydro power plant Slapy2005
214Solution proposal and delivery of equipment for island operation of heating plant KarvináDalkia Česká republika, a.s. - Heating station Karviná2005
215Heating plant terminal connection to transmitted power measurements in heating plant KarvináDalkia Česká republika, a.s. - Heating station Karviná2005
216Delivery of Power plant terminal for heating plant OlomoucDalkia Česká republika, a.s. - Heating station Olomouc2005
217Study on possibilities of providing ancillary services in heating plant OlomoucDalkia Česká republika, a.s. - Heating station Olomouc2005
218Delivery of Power plant terminal for heating station PřerovDalkia Česká republika, a.s. - Heating station Přerov2004 - 2005
219Delivery of Power plant terminal for heating station Ústí nad LabemDalkia Česká republika, a.s. - Heating station Ústí nad Labem2004 - 2005
220Putting into operation of a backed-up system for acquisition and evaluation of electrometer data in power plant OpatoviceInternational Power Opatovice, a.s. - Power plant Opatovice2004 - 2005
221System delivery for real-time production monitoring and controlling from the Dispatch centre of Pražská energetika for power plant OpatovicePRE, a.s.2005
222Control power calculation algorithm for operation in secondary active power control of nuclear power plants Bohunice and MochovceSlovenské elektrárny, a.s.2003 - 2005
223Study on control system implementation in generator room section in combined heat and power plant VřesováSokolovská uhelná, právní nástupce, a.s. - Combined heat and power plant Vřesová2004 - 2005
224Delivery of Power plant terminal for heating plant KyjovTeplárna Kyjov, a.s. - Heating station Kyjov2005
225Delivery of backed-up dispatcher graphic system (DIGRAST) and backed-up energy measurement system with air temperature measurement for Východočeská energetika company including control of power plant OpatoviceVČE, a.s.1997 - 2005
226Proposal, delivery and calibration of process flow measurement; optimization of on-cam correlation on Kaplan turbine in hydro power plant HracholuskyZČE, a.s. - Hydro power plant Hracholusky2005
227Control unit delivery for fuel sampler in power plants Mělník 1, Mělník 3, Poříčí and TušimiceČEZ, a.s.1998 - 2004
228Determination of turbo-set working diagram in hydro power plant OrlíkČEZ, a.s. - Hydro power plant Orlík2004
229Certification measurement of ancillary service “tertiary power control” in power plant Tisová 1ČEZ, a.s. - Power plants Tisová2002 - 2004
230Algorithmization, simulation and operational check of separate operation of power plants Dalešice and DukovanyČEZ, a.s. - Pumped storage power plant Dalešice2004
231Boiler control circuits tuning in heating station Přerov (boilers are connected to steam collector)Dalkia Česká republika, a.s. - Heating station Přerov2004
232Feedwater junction quality evaluation in power plant Mělník 1Energotrans, a.s. - Power plant Mělník 12004
233Tuning of boiler air system in power plant Mělník 1Energotrans, a.s. - Power plant Mělník 12004
234Quality analysis of boiler injection valves by methods of non-impact diagnostics in power plant Mělník 1Energotrans, a.s. - Power plant Mělník 12004
235Review of Grid code proposal for years 2004, 2005ERÚ2003 - 2004
236Delivery of Power plant terminal for heating plant Plzeňská teplárenskáPlzeňská teplárenská, a.s.2001 - 2004
237Ancillary service measurement before certification measurement in hydro power plants Dlouhé stráně, Lipno, Kamýk, Orlík, Slapy, ŠtěchoviceČEZ, a.s.2002 - 2003
238Level measuring device delivery for hydro power plant LipnoČEZ, a.s. - Hydro power plant Lipno2003
239Pre-complex control system test in hydro power plant ŠtěchoviceČEZ, a.s. - Hydro power plant Štěchovice2003
240Proposal and testing of the procedure of changing hardware documentation of the Westinghouse system in nuclear power plant TemelínČEZ, a.s. - Nuclear power plant Temelín2003
241Certification measurement of ancillary service “island operation capability” in power plant Tušimice 2ČEZ, a.s. - Power plant Tušimice2003
242Boiler control circuits tuning in heating plant OlomoucDalkia Česká republika, a.s. - Heating station Olomouc2003
243Certification measurement of ancillary service “primary frequency control” in power plant TřeboviceDalkia Česká republika, a.s. - Power plant Třebovice2003
244Boiler dynamic quality measurement under keeping CO and NOx emission limits and with respect to provision of ancillary servicesEnergotrans, a.s. - Power plant Mělník 12003
245State analysis of boiler actuators by methods of non-impact diagnostics in power plant OpatoviceInternational Power Opatovice, a.s. - Power plant Opatovice2003
246Turbine control circuits tuning in hydro power plant NechranicePovodí Ohře, s.p. - Hydro power plant Nechranice2003
247Pump efficiency measurement in water works KáranýPražské vodárny, s.p. - Water company Káraný2003
248Efficiency measurement in hydro power plant ČunovoSlovenské elektrárny, a.s. - Hydro power plant Čunovo (Slovakia)2003
249Optimization of on-cam correlation on Kaplan turbine in hydro power plant GabčíkovoSlovenské elektrárny, a.s. - Hydro power plant Gabčíkovo(Slovakia)2003
250Delivery of Power plant terminal for combined cycle heating station Červený mlýnTeplárny Brno, a.s. - Combined cycle heating station Červený mlýn2002 - 2003
251Development and delivery of ISA-WDOG card for external PLCKuwait2001 - 2002
252Delivery of DT-100 time displays for Praha-Ruzyně airportPraha-Ruzyně airport2002
253Optimization of on-cam correlation on Kaplan turbines in hydro power plant KamýkČEZ, a.s. - Hydro power plant Kamýk2002
254Program creation for feed water and organizer control circuit tests during putting into operation in nuclear power plant TemelínČEZ, a.s. - Nuclear power plant Temelín2001 - 2002
255Technical support during putting into operation of the Westinghouse control system during start up of nuclear power plant TemelínČEZ, a.s. - Nuclear power plant Temelín2002
256Proposal and implementation of modifications for unit control range extension in power plant DětmaroviceČEZ, a.s. - Power plant Dětmarovice2002
257Time synchronization system delivery for control systems in power plant Mělník 3ČEZ, a.s. - Power plants Mělník2002
258Technical support during test of fictive block capability to provide ancillary service “tertiary power control” in power plant Tisová 1ČEZ, a.s. - Power plants Tisová2002
259Turbo-set power control circuit tuning in power plant TřeboviceDalkia Česká republika, a.s. - Power plant Třebovice2002
260ID fan operational mode assessment and reliable boiler operation safeguarding in power plant Mělník 1Energotrans, a.s. - Power plant Mělník 12001 - 2002
261Temperature field analysis in exhaust tube before electroseparators, before and after the ID fan in power plant Mělník 1Energotrans, a.s. - Power plant Mělník 12002
262Study on boiler power increase in heating plant SETUZAEnergy Ústí nad Labem, a.s. - Heating station SETUZA2002
263Proposal of airflow system, burners reconstruction and boiler control in company Lovochemie LovosiceLovochemie, a.s. - Lovochemie Lovosice2002
264Boiler control circuits proposal in heating plant OstrovOstrovská teplárenská, a.s. - Heating station Ostrov2002
265Project and execution of tests for connecting of the Island of power plant Burštýn to UCPTEWEPS Lvov - Power plant Burštýn (the Ukraine)1998 - 2002
266Delivery of Power plant terminal for power plant Burštýn and upgrade of the Terminal for data communication with unit control systems and with control system of the dispatch centre RDC LvovWEPS Lvov - Power plant Burštýn (the Ukraine)2000 - 2002
267Turbine guarantee measurement after reconstruction in hydro power plant LadceHydro power plant Ladce2001
268Time synchronization system delivery for computer network in Praha-Ruzyně airportPraha-Ruzyně airport2001
269Implementation of island operation in hydro power plant Orlík and SlapyČEZ, a.s.2001
270Outlet steam pressure control optimization in power plant ChvaleticeČEZ, a.s. - Power plant Chvaletice2001
271Delivery of Power plant terminal for heating plant KarvináDalkia Česká republika, a.s. - Heating station Karviná2001
272Certification measurement of ancillary service “secondary power control” in heating plant KarvináDalkia Česká republika, a.s. - Heating station Karviná2001
273Calibration of combustion products flow meter in power plant Mělník 1 using three independent methodsEnergotrans, a.s. - Power plant Mělník 12001
274Study on possibilities of provision of selected ancillary services in heating plant Plzeňská energetikaPlzeňská teplárenská, a.s.2001
275Expertise during Controlled Heating Supply System identification in the City of PraguePražská teplárenská, a.s.2001
276Dynamic tests in hot-water pipes network of Pražská teplárenská companyPražská teplárenská, a.s.2001
277Preparation of fictive block operation for provision of the ancillary service “secondary power control” in department Teplárna in combined heat and power plant VřesováSokolovská uhelná, právní nástupce, a.s. - Combined cycle Vřesová2001
278Delivery of Power plant terminal for heating plant StrakoniceTeplárna Strakonice, a.s. - Heating station Strakonice2001
279Study on possibilities of provision of selected ancillary services in combined cycle heating station Červený mlýnTeplárny Brno, a.s. - Combined cycle heating station Červený mlýn2001
280Proposal and tuning of control circuits for fluidized bed boiler in heating plant KomořanyUnited energy, a.s. - Heating station Komořany1999 - 2001
281Synchronous valve tuning in hydro power plant VydraZČE, a.s. - Hydro power plant Vydra2001
282Creation of electronic documentation of the nuclear power plant Temelín–Westinghouse and DASOR systemsČEZ, a.s. - Nuclear power plant Temelín2000
283Implementation of island operation in power plant Prunéřov 1ČEZ, a.s. - Power plant Prunéřov 12000
284Implementation of island operation in power plant Tisová 2ČEZ, a.s. - Power plants Tisová2000
285Implementation of superior control of steam pressure in steam collector in power plant Tisová 1ČEZ, a.s. - Power plants Tisová2000
286Project for real-time active power control of power plant Opatovice from the Dispatch centre in of company Východočeská energetika companyInternational Power Opatovice, a.s. - Power plant Opatovice2000
287Upgrade of the Communication Processor in power plant Opatovice for real-time active power control from the Dispatch centre of Pražská energetikaInternational Power Opatovice, a.s. - Power plant Opatovice2000
288Hydraulic tests of penstock Švařec – ČebínSdružení VOV2000
289Control system proposal for coal gasification technology in department Paroplyn in combined heat and power plant VřesováSokolovská uhelná, právní nástupce, a.s. - Combined cycle Vřesová2000
290Guarantee measurement of Francis turbine and long penstock before reconstruction in hydro power plant PráčovVČE, a.s. - Hydro power plant Práčov2000
291Kaplan turbines guarantee measurement in hydro power plant ŽagańZEW Dychow, S.A. Polsko - Hydro power plant Žagań (Poland)2000
292Unit control range extension in power plants Chvaletice, Počerady and Tušimice 2ČEZ, a.s.1999
293Implementation of island operation in power plant Mělník 3ČEZ, a.s. - Power plants Mělník1999
294Guarantee measurement of dynamic and control qualities of fluidized bed boiler in power plant TisováČEZ, a.s. - Power plants Tisová1999
295Backed-up system delivery for electric energy measurement for Západočeská energetika companyZČE, a.s.1998 - 1999
296Delivery of Border substation Terminals (Albrechtice, Lískovec a Nošovice)ČEPS, a.s.1998
297Primary frequency control optimization in hydro power plants Dalešice, Orlík, Lipno a KamýkČEZ, a.s.1998
298Combustion optimization and boiler efficiency measurement in power plant Vojany 2Slovenské elektrárny, a.s. - Power plant Vojany (Slovakia)1998
299Delivery of Power plant terminals for power plants of ČEZ, Plc. (Chvaletice, Dalešice, Dětmarovice, Dlouhé stráně, Dukovany, Hodonín, Ledvice, Mělník, Poříčí, Počerady, Prunéřov 1, Prunéřov 2, Temelín, Tisová, Tušimice)ČEZ, a.s.1994 - 1997
300Measuring and evaluating of system tests of UCTE/CENTRELČEZ, a.s.1995
301Island operation implementation including real island tests of Ostrava district in power plant DětmaroviceČEZ, a.s. - Power plant Dětmarovice1995
302Model of Czech electrical power systemČEZ, a.s.1993
303Model of Slovak electrical power systemSlovenské elektrárny, a.s.1993

OSC a.s., Staňkova 18a, P.O.Box 111, 612 00 Brno, Czech Republic